Paving Schedule
Monday 6/23 to Thursday 6/26 (4 days), PAVEMENT GRINDING
The streets will be done in the following order:
1. Hickory
2. Grant
3. Madison
4. Garfield
5. County Line Rd
6. The Lane
Friday 6/27 the contractor will start PAVEMENT PATCHING
for 2-3 days
Tuesday 7/1 Thursday 7/3, PAVING BINDER COURSE for
3 days
AFTER 7/4, MANNHOLE ADJUSTMENTS will resume. After concrete
has cured, the contractor will place the final SURFACE COURSE
Ogden Avenue
*update*
The remainder of the Ogden Avenue road construction will
start on Friday, June 13 and will take several weeks to
complete.
Beginning
Wednesday, March 26, 2008, Ogden Ave.(US Rte 34) road construction
activity will resume. Permanent lane closures will be necessary
to safely complete the preliminary stages of the road widening.
One lane in each direction, between County Line Rd and Oak
Street, will be open to traffic. Due to this traffic staging,
left turn movements from west bound Ogden to south bound
County Line Rd will be prohibited. Motorists will be detoured
to Oak Street and Fuller Street then on to County Line Rd.
Although flagging operations and traffic control devices
will be in place to assist with local traffic flow, delays
will be experienced. Motorists are encouraged to use the
posted detour route. Local business access will be maintained
during all phases of the project.
If there
are any questions concerning this notice, please contact
the Engineering Dept. for the Village of Hinsdale at (630)
789-7029.